Pathway IT Project Management

Expert Project Management Support
Pathway IT Consultants provides expert project management support in addition to training. In this article we’ll look at different aspects of project management and critical activities that make the difference between success and failure.
Delivering IT projects is extremely difficult, and this is proven by the high failure rate. At least 65 per cent of projects are stopped before cutover, go over budget or don’t deliver the expected benefits. This is an astonishing failure rate, and it has been consistent for over two decades.
Our practical project management consultancy is based on lessons learnt delivering critical projects and transformation programmes across a number of industry sectors. (Including charity, transport, finance, hotels, automotive and education.) We have specialist knowledge in the following areas:
Pathway project management support can be tailored to your specific requirements, whether it’s advice on a specific project issue, methodology, mentoring, project management, project health checks or project rescue.
Methodology Selection and Enhancement
Despite decades of use of Waterfall, PRINCE, and Agile methodologies, the failure rate of at least 65 per cent remains consistent. Gaps in the methodologies are a major contributing factor to this.
The project manager’s skill and knowledge are critical. Knowing when to combine methodologies or add additional activities will make the difference between delivery of a system that adds value or a costly failed project after months or years of effort.
It is important to clarify that this statement is not a criticism of the methodologies. They can be excellent and have been used to deliver many successful projects. However, despite the increased use of methodologies, the failure rate is not improving. There are many reasons for this:
The following methodology support is available:
Critical Activities Regardless of Methodology
There are several critical actions that can make the difference between success and failure. The following activities are proven to reduce risk, but some of the activities are not a prominent feature of Agile or Waterfall methodology.
Dress rehearsals
Along with professional project initiation, dress rehearsals are the most critical activity to ensure a successful project. Dress rehearsals will draw attention to problems not encountered during any test phase. The users will approach go-live with a high level of confidence because they have already completed critical business scenarios in the dress rehearsals.
Dress rehearsals are not a rerun of UAT. They are a separate activity with different objectives.
Strong project governance
Effective governance is critical. Ensure appropriate project governance is in place and everyone on the team understands it. This includes the ability to escalate issues and resolve them quickly.
Benefits management and critical success factors
Agree on the critical success factors at the beginning of the project. This doesn’t need to be a long list. In fact, having five or ten critical success factors keeps the team and stakeholders focused on delivering the most important elements.
Ensure you can measure critical success factors to confirm they have been delivered. It's gratifying to review these after delivery and have stakeholders agree that all priority items were delivered.
Risk management
Risk management is critical throughout the project and will come under sharp focus as cutover approaches.
Risk management should be based on objective criteria. Without this, opinions of the level of risk will vary widely. Pathway takes a pragmatic approach using a spreadsheet with risk weighting. The yes or no answers only take a few minutes to complete, and this provides a low, medium or high risk score.
Deliverables
Regardless of methodology, agreeing on and tracking deliverables is key to managing a successful project. Whether it is the deliverable from a sprint in Agile or a milestone in a Waterfall project plan, stakeholders will require updates on progress. Understanding, tracking and managing dependencies between deliverables is essential.
Project initiation
This is a critical activity. Issues with project initiation are a major factor in eighty per cent of failed projects.
The level of documentation depends on the size and complexity of the project. The following items need to be considered:
Please include all relevant sections in the project initiation phase, regardless of the methodology used.
Project budget
Please consider the following:
Communication plan
On some projects, the activities in the communication plan commence close to going live. The plan should be prepared during the early phases of the project, and communication should be an integral part of the complete project.
Quality assurance is a separate activity, and it is essential for successful project delivery.
Be wary if anyone says, ‘Quality assurance is just part of everyone’s activities.’ This statement isn’t correct, but it is heard on many projects. The quality plan should specify the person responsible for quality assurance and measurement criteria.
Quality assurance is required for all activities, but data quality assurance is an area that requires additional diligence.
Estimating
Universities have conducted studies to determine the accuracy of estimates versus actual time taken to complete tasks. They concluded that tasks take, on average, over twice as long to complete compared to the estimates. Optimism and not considering potential issues and blockers contribute to the problems with underestimating.
The studies found that people are able to estimate other people’s tasks more accurately than their own. Not using historic data to assist with estimating is another cause of poor estimating.
Resource planning
It is good practice to assume that full-time project resource will not be available for more than 80 per cent of the time. This is to account for holidays and illness.
If people are working on the project in addition to their day jobs, make sure there is a contingency plan in case they are needed to resolve urgent BAU issues. These people may be Subject Matter Experts (SMEs), and it may not be easy to find a replacement for them.
Work packages
Work packages are a valuable tool to control time and cost. They distil work into an easy-to-understand one-page document that includes resource, cost, date and deliverable information.
Cutover
Include cutover planning from the start of the project. (Strategy, approach, target dates, etc.)
Develop a detailed cutover plan that includes dependencies, activity, resources, communication, checkpoints and post-go-live project support. Complete a cutover dress rehearsal to ensure that all timings are correct.
Handover to support
Handover to the support team is critical for a smooth cutover. Please include handover activities in all plans. Ensure the handover documentation is fit for purpose.
Review the documentation at regular intervals starting early in the project. Don’t leave the task until the last minute and rush the preparation of this.
Include the support teams in the dress rehearsals. Add a failure scenario to ensure that everyone from the end user to third-level support understands the process. Also, involve the support team in the preparation of the support Service Level Agreement. (SLA)
Post go-live project support
Please consider the following in the planning process:
Summary
Every project is unique. Knowing when to combine methodologies or add additional activities will make the difference between delivery of a system that adds value or a costly failed project after months or years of effort.
We hope you have found this article useful. Please let us know if you need support with any aspect of your projects.
Trade mark acknowledgements
IBM® is a registered trade mark of International Business Machines Corporation.
Agile Business Consortium trade marks: DSDM®, Atern®, AgilePM®, AgilePM® for Scrum, AgileBA®, AgilePgM® and AgilePfM™ are registered trade marks of Agile Business Consortium Limited. AgilePF™ is a trade mark of Agile Business Consortium Limited.
AXELOS trade marks: ITIL® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. MSP® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PRINCE2® is a registered trade mark of AXELOS
Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl Logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.
APMG trade marks: The APMG-International Agile Project Management and Swirl Device logo is a trade mark of The APM Group Limited. The APMG-International Swirl AgileBA Device is a trade mark of APM Group Ltd. The APMG-International Swirl AgilePgM Device is a trade mark of APM Group Ltd.
All other trade marks are acknowledged.
Pathway IT has proven project management expertise, and flexible support is available.
Please contact us if you require additional information.
Copyright Pathway IT Consultants Limited 2025
Pathway IT Consultants Registered Office: Mansion House, Manchester Road, Altrincham, Cheshire, WA14 4RW
Company Number 6200503
VAT Registration Number 975 9277 52
Version 0.18